Milton 10 CES – const progress -March 7/22 / We are going the right way!

Blog Summary: (AI Summaries by Summarizes)
  • The post discusses the importance of executive summaries for busy individuals.
  • It emphasizes the need for concise and clear communication in executive summaries.
  • Executive summaries should provide a brief overview of the main points and key findings.
DCIM\110MEDIA\DJI_0851.JPG

Roof- we appear to be 55% watertight.





Painters are now onsite starting door frames.


Major clean up is underway. Recommend painters complete hallways ASAP / to allow placement of ceramic tile.


Main floor – concrete locker base needed.


Pouring of concrete /stage/ scheduled this week.


Work proceeding / Main Mech Rm / pumps, sheet metal, piping as we are now watertight.👍👍

Main floor- fire spray re- steel beams required.


Work is progressing well /and as our roofers proceed/ allows us to expedite tasks re – interior. We are going the right way.🍺🍺🍺