Milton 10 CES- Occupancy Scheduled Mid June!

Blog Summary: (AI Summaries by Summarizes)
  • The post discusses the importance of executive summaries for busy individuals.
  • It emphasizes the need for concise and clear communication in executive summaries.
  • Executive summaries should provide a brief overview of the main points and key findings.

School roof appears 100% watertight. Scheduled next is childcare as material is placed on roof. Note: We require cap sheet installed ASAP allowing placement of Roof Top Units re- curbs.

We are pushing Occupancy – Mid June. Painters and flooring contractors are progressing well as we await the arrival of Millwork. Exterior / brick veneer is starting and close behind is sidewalk and curb. Mid June is fast approaching and now we need to “giddy up”