Nelson High School – April 12/21- Reno update April 12, 2021 Auto Body – sheet metal contractor installing duct. New Cafeteria- drywall contractor working on bulkhead.Entrance to new Library- Drywall to be removed soonWaiting for permanent power to our new addition. New Kitchen- placement of equipment near completion. New Library- major cleaning has started.New Library- painting is near completionNew Library- light fixtures / ceiling/ are in place. Masonry Contractor is onsite cleaning brick. Share this:MoreLike this:Like Loading... Related