AVB spray has now been applied beneath bridge.

Kitchen Equipment receiving final hook-ups. Scheduled for completion end of this week.

Library – Decorative [sound ] panels have been installed.

Rooms adjacent to library are now painted.

Elevator- foundation walls have been built- Ready for back-fil.

Body-shop classroom- metal panel is being installed.
We are pushing for completion / end of this month.🍺🍺