Hi Anil,

I have the following scheduled for the paving of the west parking lot, trench restoration and concrete work.

August 15th-placement of 2” gravel

August 16th-20th-sidealks and curbs (layout to be provided by TRP)

Aug 21st-22nd-3/4” stone and fine grading

August 23rd-paving

August 24th-line painting.

Mike Zaffino | West Region Manager