St. Kateri Tekakwitha – const progress – Nov 13, 2023

Blog Summary: (AI Summaries by Summarizes)
  • Metal deck for the west side roof is scheduled to arrive and will be promptly installed, contributing significantly to the overall construction progress.
  • All steel will be onsite by the end of this month, marking a significant milestone in the project.
  • Windows installation is scheduled for the middle of December, providing aesthetic appeal and enhancing the building's functionality and insulation.