Stage:
Sprinkler contractor has now placed their pipe! We await the return of our drywall contractor (Cannan) installing grid. Once installed allows the placement of lights, sprinkler heads and diffusers!
Precast arrives Monday! I am told hollow metal frames (doors) arrive tomorrow! Also needed lintels ( galvanized) and plates!