St. Mark CES- placement of ceiling tile

We have scheduled the placement of ceiling tile in ( classrooms, library and admin offices starting next Wed Aug 15th. We are asking all trades to complete their work / above ceilings/ prior to Wed. Also, all consultants please proceed with your inspections.

We have also scheduled the placement of ceiling tile / Hallways/ starting a week later Aug 22. The same applies as above.

Up to date ceiling schedule T-bar

We now have full power. Nitesh to receive the “Atta Boy” award for August👍

We have started pouring SOG – addition

Excavation (cutting) behind portables continues.