Rain most of the day:
Going Foward: Metal Deck [roof] is now in place. Waiting for plywood [ parapet] – curbs [RTU] to be set in place. GRRC [roofing] needed soon
Windows scheduled for Monday [ installation] – followed by spray [AVB] then installation of brick veneer. Painters are on deck.

Note: we need to start thinking about heat, in the building, as finishing trades will be arriving soon. Our next milestone is T-bar ceiling – the week of Dec 10th- all above work to be in place.

Opening for lift [stage area] ongoing