Steel to carry the load for RTU is now a challenge! Our friends from Mirage Steel are quickly drawing up shop drawings! We hope to have approved drawings Monday at the latest! Then the team from Neivex / our masonry contractor/ need to be onsite installing bearing plates! This is our “bullseye”- may the force be with us!
Our Sprinkler contractor is now installing pipe👍
We need all existing mechanical equipment and duct removed “NOW”
Plenty of removal needed
We want to start footings re- addition Monday🎯🎯🎯