We are now into full demolition mode as we prepare to rebuild!
Sprinkler contractor is running pipe and is doing well👍👍 . We can discuss at tomorrow’s meeting, but all ceilings need to come down to allow: sprinkler- metal duct- and steel, supporting RTU’s! Tomorrow will be an important meeting giving us direction! I highly recommend anyone associated with this project to attend🎯
Excavation (cut) is in full gear behind school! Preparing footprint for the portables!
As per drawing! VCT located in classrooms has been removed!
Most important! We need all existing duct and air handling units removed ASAP. 🎯🎯