Work has started as we push for Sept 4th / school opening!

Ceiling tile and T bar grid will be removed today! It is important all remaining wire is secured preventing damage! Our major milestone is new T-bar ceiling starting first week of August! We need all work above ceilings complete prior to August 1st

Southeast corner

Southwest corner

Northwest corner- footings re-addition scheduled for Monday

Northeast corner

Excavation has started