Cutting to expose footprint (addition) is near completion. Contractor has told me footings start tomorrow or Monday at the latest👍
Demolition continues as pic below reveal wall being demolished.
Welding continues in library
Providing access re- transfer air and supply air duct near completion ( classrooms)
Sheet metal contractor has duct onsite- contractor is starting to install hangers!