We need contractor to form footings NOW. We have just pumped out water and rain is forecast for Friday! also note: pls have hollow metal frames (doors) onsite prior to coming above ground.🐢🐢🐢🐢🐢🐢🐢🐢

Mechanical contractor: pls provide undergrounds (addition) ASAP

Mech curbs are now placed on the roof! George ( GRRC) pls connect with Scot ( our super) as we would like curbs to be watertight first of next week. RTU’s arrive July 30th

Contractor cutting floor in the food nutrition room

We are now starting to hang metal duct 👍