St. Mark CES- The final push

To all trades/ as agreed by everyone: starting Aug 22nd @ 7 am the T-bar gang are returning to complete all ceilings. Make sure all your wall penetrations are sealed above ceilings. Also, All units are hung and piping insulated. Fire verification happens on Monday the 27th and all ceilings should be fully tiled. We do not want to run anyone over so be prudent and get your work done. Also: do not lose sight of the addition as we are moving at a lightning pace. We are pushing completion/ addition/ prior to Christmas. ⛄️⛄️⛄️⛄️⛄️⛄️