Windows are being installed: Waiting For
- installation plywood parapet wall needed
- curbs [RTU] to be placed and openings cut
- roof drains to be connected
- locker base and concrete pads entrance – to be poured
- once windows installed – AVB to be applied followed by brick veneer
- installation of retaining wall

Roofing contractor needed soon
Painters on deck – interior heat required
Ceramic tile hallways starts hmmm! in 2 weeks.

Elevator lift / stage. Base being formed.