We are β€œrock-n- roll” on the exterior. Arrowhead is onsite setting string for concrete curb. All curbs to be poured tomorrow.πŸ‘πŸ‘πŸ‘πŸ‘πŸ‘

Laying out string [curb] SW corner
Curb layout front
Rear of building
Preparing to pour SOG garbage enclosure
T- bar grid starts tomorrow πŸ‘πŸ‘
Starting installation of Millwork. Ready for white and tack board
Washing brick- waiting installation of gas meter.