St. Nicholas- 57 days remaining

57 days to go
Heaters are now onsite [3] and fans. Everstrong is sealing off the building and fans to be operating tomorrow. Konrad, Max can start Monday.👍👍
Building needs a major clean-up [broom]. This is to be complete no later than tomorrow.
Mike [ Kor} you are good to go and deliver all Millwork Monday. Installation /classrooms/ Has the green light.🔦🔦
Work carries on in mechanical room. We need to push here.