T-bar ceilings start Nov 1st. All trades Work above /to be complete.
59 days remainingLocates for gas line have just been identified [painted]. Hopefully installation / gas line will be installed soon resulting in heat for the building.Roofers are working over the gym. Classrooms /North wing/ Now watertight.roofers working over gym.plywood needed / gymplywood needed library