St. Nicholas 67 days remaining

Drain land cutting down front of building. Scheduled for completion mid-end of this week
Aerloc installing window frames. Glass scheduled for this Thursday and Friday
Metal doors have all been painted. Everstrong to install doors and hardware this week.. We require electrical room with door and lock.
Ceramic tile has arrived. Starting end of the week.
Painters are starting 2nd coat today.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: