St. Nicholas CES- Nov 1st update

The guys are enclosing the building as we pump in heat for Monday
Z-Girts are being installed. Aerloc we need window frames and glass installed Now!!!!!!
Where are we with handrails???
Konrad, classrooms 2nd floor are ready – flooring. Please contact Anthony Re- scheduling
Gym, to be emptied starting Monday. This allows M&E contractors to do their work above. Once work is complete above allows painter to do their work.
Wiring / parking area / is now roughed in.👍👍
Anvi Mechanical has arrived onsite.