St. Nicholas CES- Oct 10, 2019- progress

We are coming down the home stretch!
Oakville Hydro is on site today!
Steel is now installed garbage enclosure
Aerloc scheduled to ariive this afternoon
The site is now busy
Preparing for brick veneer!
road and sidewalk have been patched.
Painters starting / front
wall angle trim being installed in classrooms. Note: T-bar ceilings start Nov 1st at the latest.
Our Roofers