We have now confirmed fire verification booked for Dec 9th. All ceilings are near completion.





-string for concrete curb is being placed
– concrete curb poured tomorrow – parking area
-Asphalt paving next week.
Note: School Board furniture arrives during the Christmas Holidays. All Floors need to be in place.