Where are we with boarding of drywall ?? Many studs have been erected and in need of drywall.I understand underground piping has been inspected and concrete will be applied starting Wednesday.
Anvi Mechanical has the “Bullseye” existing units are being ripped out. Ceilings are now exposed allowing installation of new units, metal duct, gas piping etc. I understand lighting fixtures will be arriving soon. We need these tasks complete ASAP.Curbs re- roof top units are now onsite. We need curbs placed ASAP, supported from beneath and watertight prior to delivery of new units. Where are we with additional parking???