Elsie MacGill Secondary School – const progress- July 30/21
Flyover July 30 2021 LAST MONTH
Drone Pilot
Flyover July 30 2021 LAST MONTH
Work is progressing well. Scheduled pouring SOG next week followed by pre-cast the week after. OWSJ /roof/ needed soon re- childcare.
Masonry contractor building walls / childcare. Pushing pre-cast Aug 11th.
School starts in 43 days.
Click on video below as the song reflects the picture
Mario and I are blasting off – Just like Jeff Bezos- except we have no money. We are in dire need of Slab on Grade???????
Above- Masonry now complete / Tech rms/ Ready for paint. New Elevator- waiting on the arrival of scaffold. 48 days remaining until start of school.👁
You must be logged in to post a comment.