Month: July 2021
Milton #10 CES- construction progress- July 28/21
Work is progressing well. Scheduled pouring SOG next week followed by pre-cast the week after. OWSJ /roof/ needed soon re- childcare.
Milton #10 CES – const progress- July 26/21
Masonry contractor building walls / childcare. Pushing pre-cast Aug 11th.
Sitting On The Dock by The Bay
Click on video below as the song reflects the picture
Milton #10 CES- July 21/21 – const progress
Mario and I are blasting off – Just like Jeff Bezos- except we have no money. We are in dire need of Slab on Grade???????
Nelson High School – July 21/21 Const progress
Above- Masonry now complete / Tech rms/ Ready for paint. New Elevator- waiting on the arrival of scaffold. 48 days remaining until start of school.👁


Flyover July 30 2021 LAST MONTH
Share this:
Like this: