Blog post
N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion
The current project has reached a standstill due to trades suspected of prioritizing work at other schools ahead of the impending September closure. Our team urgently requires trades on-site, as completing our school is paramount. We are unable to progress until the […]
- | Leave a Comment on N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion
Milton 11 CES – Progress on Backfilling Foundation Walls
It was exciting to witness our contractor beginning the footings at the front of the building. We are in urgent need of backfilling the existing foundation walls, which is a crucial step in our construction process. Once those walls are backfilled, it […]
N E Oakville HS – Rooftop Units Installed: Construction Project Update
The construction project has reached significant milestones, as all rooftop units are now installed, achieving a 100% watertight status. The gym floor is equipped with acoustic flooring, anticipating the upcoming topping pour. This week marks the commencement of the flooring contractor’s work, […]
Milton 11 CES – Construction Progress Update: Foundation Footings Begin
Our friends at D’Orazio are making great strides in the northwest corner, enabling us to advance our footing work. This week, we are commencing the footings on the front half of the building. Soon, we will begin backfilling our foundation walls, which […]
N E Oakville High School – Challenges in Project Timeline: Flooring Delay Impact
Great news! The remaining rooftop units have arrived, and the crane is now onsite, ready for action. Once we successfully install these units, we will be able to pour the topping in our gym, marking a significant step forward in our project. […]
- | Leave a Comment on N E Oakville High School – Challenges in Project Timeline: Flooring Delay Impact
Milton 11 CES -Foundation Progress Update: Key Milestones Achieved
Project Update: Foundation Progress Our foundation walls are now well underway, marking a significant step forward in our construction timeline. Following the completion of the foundation walls, our mechanical and electrical contractor will begin the placement of underground utilities. Once this phase […]
Our New Grimsby Go Station – The Push Is On!
Three weeks progress! THE PUSH IS ON!!
N E Oakville H S – Rooftop Unit Delivery and Site Progress Update
It now appears that the delivery of our remaining rooftop units has been rescheduled for next Tuesday. We need these units in place to ensure our gymnasium remains watertight. The masonry contractor is cleaning the walls in the childcare area, allowing our […]


1 min- 0 0
-
43
-
1 day ago
- 9
Flooring Contractor scheduled for Monday?? Our site is rather quiet today as we eagerly await the arrival of our finishing trades. The masonry work is nearing completion with the brick veneer almost finished. Following this, all attention will shift to Lakeside contracting […]
Share this:
Like this: