News
N E Oakville High School – const progress – Oct 13
As we approach December 2nd this year, we reflect on the challenges we faced last year and the progress we’ve made since then. It is crucial that we ensure adequate
Continue readingN E Oakville High School – const progress – Oct 13
Milton 11 CES – construction progress – Oct 13 2026
The masonry contractor is working on the above-ground structures, while the plumbing contractor needs to install underground piping on the west side. To expedite progress, it is crucial to collaborate
Continue readingMilton 11 CES – construction progress – Oct 13 2026
N E Oakville High School – construction progress – October 9
The flooring installation in our classrooms has put us behind schedule, as we’re still waiting on the arrival of the installers. Millwork cannot proceed until the finished floor is in
Continue readingN E Oakville High School – construction progress – October 9
Milton 11 CES – construction progress – Oct 6 2026
The masonry contractor is currently advancing with the construction of walls above ground. However, a significant challenge we face is the delay in receiving steel lintels and metal door frames,
Continue readingMilton 11 CES – construction progress – Oct 6 2026
North East Oakville High School – Oct 6 2026
As we approach the final stages of our project, various tasks are coming to fruition. Our flooring contractor has been diligently preparing the classrooms for the installation of the finished
Continue readingNorth East Oakville High School – Oct 6 2026
North East Oakville High School – const progress – October 1
As we continue making significant progress on our classroom renovations, I wanted to inform our flooring contractor that all access from the cafeteria to the upper floors will be closed
Continue readingNorth East Oakville High School – const progress – October 1


You must be logged in to post a comment.