News
N E Oakville H S – Project Update: Tile Installation and Progress Insights
As we embark on the final stages of our project, the third-floor hallway is currently seeing the installation of floor tiles, with plans to extend this work into the classrooms
Continue readingN E Oakville H S – Project Update: Tile Installation and Progress Insights
N E Oakville High School – Final Phase of School Construction: Key Progress Updates
As we enter the final phase of our project, progress is accelerating significantly. Lakeside is currently onsite grading our parking area, while our masonry contractor is busy removing their equipment
Continue readingN E Oakville High School – Final Phase of School Construction: Key Progress Updates
N E Oakville High School – Countdown to School Opening: Flooring and Millwork Updates
As our flooring contractor continues to work, we find ourselves in a race against time. Additional staff are essential to meet our deadline, but their presence is truly appreciated. We
Milton 11 CES – Construction Progress Update: Foundation Walls and Timely Installations
Work is proceeding smoothly as foundation walls are being constructed. Our general contractor is poised to begin backfilling these walls shortly. Meanwhile, the mechanical contractor is currently NOT onsite to
Fast-Track Approach for Grimsby GO Station Development
Provide a construction for the Grimsby Go Station starting in July 2026 and completion late summer early fall 2027. Yes. Based on the July 2026 construction start and the currently stated summer 2027
Continue readingFast-Track Approach for Grimsby GO Station Development
Milton #11 School Opening: Fast-Track Construction Schedule
Provide a construction schedule for Milton 11 catholic elementary school allowing the opening of September 2027 Yes. Based on the current information available as of August 28, 2026, a September 2027 opening
Continue readingMilton #11 School Opening: Fast-Track Construction Schedule
Milton 11 CES – Foundation Wall Construction Progress Update
We are excited to share that we have successfully completed 100% of the footings, and we’re now preparing to construct our foundation walls. The southern area of the building remains
Continue readingMilton 11 CES – Foundation Wall Construction Progress Update
N E Oakville High School Project: Milestones and Progress
Office I asked Ai to provide a summary and review of our project: Below is the result Yes. I researched the project timeline and can give you a construction-progress timeline beginning
Continue readingN E Oakville High School Project: Milestones and Progress
N E Oakville High School – Summer Project Update: Flooring and Exterior Work Insights
As we find ourselves in the midst of a summer lull, there is a sense of complacency that needs shaking off. We are optimistic that our flooring contractor will commence


You must be logged in to post a comment.