St. Mark CES- we are turning the corner!

2 cannibals are eating a clown
One cannibal turns to the other cannibal and says
โ€œDoes this taste funny to youโ€

Steel has arrived ( Mirage) re- roof top units๐Ÿ‘๐Ÿ‘๐Ÿ‘

Steel is being placed( RTU) erector is placing steel

Mechanical Room- demolition near completion

Electrical distribution panels are onsite.

We still need gas meter removed to allow sprinkler and water pipe to enter building.๐Ÿข๐Ÿข

Footings re- additions are now ready for forming. I am told contractor will be onsite tomorrow.

Curbs are being built and then placed. By end of week ready to roof (watertight) curbs. Roof Top Units arrive July 30th. ๐Ÿ‘€

https://larryarbuckle.com

Schedule – asphalt / sidewalks & curb

Hi Anil,

I have the following scheduled for the paving of the west parking lot, trench restoration and concrete work.

August 15th-placement of 2โ€ gravel

August 16th-20th-sidealks and curbs (layout to be provided by TRP)

Aug 21st-22nd-3/4โ€ stone and fine grading

August 23rd-paving

August 24th-line painting.

Mike Zaffino | West Region Manager

https://larryarbuckle.com

1731 St Mark Meeting Minutes MOM 3

https://larryarbuckle.com

Begin forwarded message:

From: “Mike Zaffino” <Mikez>
Date: July 13, 2018 at 10:14:50 AM EDT
To: “‘Anil Gokarn'” <agokarn>, “‘John Patsas'” <johnp>, “‘Larry Arbuckle'” <larryarbuckle>
Cc: <tims>, “‘Duffield, Josh'” <DuffieldJ>, “‘Scott Iseppon'” <ScottI>
Subject: RE: 1731 St Mark Meeting Minutes MOM 3

St. Mark CES- renovation- โ€œWelcome to the Alamoโ€

The hand to hand combat continues as we push for a Sept 4th completion!

We are now ready for our footings re- addition

Plenty of metal duct and fittings are arriving๐Ÿ‘

Demolition continues as we cut opening for door

I understand the guys will be working in mechanical room this week-end

Metal duct stored in classrooms

The pace has picked up as there is plenty of noise inside the school! No standing around on this job๐Ÿ’ช

https://larryarbuckle.com