Blog post
Milton 11 CES-Foundation Progress: 60% Complete and Next Steps
Foundation work is progressing well, with approximately 60% of the foundations completed. The foundation walls are set to receive grout shortly, paving the way for backfilling. This crucial step will enable our M&E contractors to install the underground piping and equipment needed […]
Milton 11 CES – Current Progress on Footings Work
Our footings work is currently in progress and presents some complexities. As of now, the crew reports that we are approximately 50% finished. We are awaiting the grout needed for our foundation walls, which is a critical step before proceeding with backfill […]
N E Oakville High School – Optimizing Project Timelines: Curtain Wall Installation Insights
It was a pleasure to see Aerloc onsite installing the curtain wall in our cafeteria. The installation not only enhances our space but also allows other trades to proceed with their work efficiently. However, we are currently facing a challenge as our […]
- | Leave a Comment on N E Oakville High School – Optimizing Project Timelines: Curtain Wall Installation Insights
N E Oakville H S – Upcoming Finishing Touches: Our Construction Journey
Flooring Contractor scheduled for Monday?? Our site is rather quiet today as we eagerly await the arrival of our finishing trades. The masonry work is nearing completion with the brick veneer almost finished. Following this, all attention will shift to Lakeside contracting […]
N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion
The current project has reached a standstill due to trades suspected of prioritizing work at other schools ahead of the impending September closure. Our team urgently requires trades on-site, as completing our school is paramount. We are unable to progress until the […]
- | Leave a Comment on N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion
Milton 11 CES – Progress on Backfilling Foundation Walls
It was exciting to witness our contractor beginning the footings at the front of the building. We are in urgent need of backfilling the existing foundation walls, which is a crucial step in our construction process. Once those walls are backfilled, it […]
N E Oakville HS – Rooftop Units Installed: Construction Project Update
The construction project has reached significant milestones, as all rooftop units are now installed, achieving a 100% watertight status. The gym floor is equipped with acoustic flooring, anticipating the upcoming topping pour. This week marks the commencement of the flooring contractor’s work, […]
Milton 11 CES – Construction Progress Update: Foundation Footings Begin
Our friends at D’Orazio are making great strides in the northwest corner, enabling us to advance our footing work. This week, we are commencing the footings on the front half of the building. Soon, we will begin backfilling our foundation walls, which […]


2 min- 0 0
-
12
-
2 hours ago
- 3
As we approach the culmination of our journey, we are eager to push forward with our final trades. It was a pleasure to witness our flooring contractor diligently loading floor tiles, ready to commence installation. This proactive approach sets a positive tone, […]
Share this:
Like this: