Blog post

Milton 11 CES – Current Footing Progress: Key Updates on Construction

Footings are currently in progress and once they are poured, we will reach approximately 75% completion of the footings.. The backfilling of the foundation walls has commenced, enabling the mechanical contractor to install and bury their underground piping and equipment. During my […]

Read More

N E Oakville High School – Project Progress Update: Flooring and Installation Milestones

As we approach the culmination of our journey, we are eager to push forward with our final trades. It was a pleasure to witness our flooring contractor diligently loading floor tiles, ready to commence installation. This proactive approach sets a positive tone, […]

Read More

Milton 11 CES-Foundation Progress: 60% Complete and Next Steps

Foundation work is progressing well, with approximately 60% of the foundations completed. The foundation walls are set to receive grout shortly, paving the way for backfilling. This crucial step will enable our M&E contractors to install the underground piping and equipment needed […]

Read More

Milton 11 CES – Current Progress on Footings Work

Our footings work is currently in progress and presents some complexities. As of now, the crew reports that we are approximately 50% finished. We are awaiting the grout needed for our foundation walls, which is a critical step before proceeding with backfill […]

Read More

N E Oakville High School – Optimizing Project Timelines: Curtain Wall Installation Insights

It was a pleasure to see Aerloc onsite installing the curtain wall in our cafeteria. The installation not only enhances our space but also allows other trades to proceed with their work efficiently. However, we are currently facing a challenge as our […]

Read More

N E Oakville H S – Upcoming Finishing Touches: Our Construction Journey

Flooring Contractor scheduled for Monday?? Our site is rather quiet today as we eagerly await the arrival of our finishing trades. The masonry work is nearing completion with the brick veneer almost finished. Following this, all attention will shift to Lakeside contracting […]

Read More

N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion

The current project has reached a standstill due to trades suspected of prioritizing work at other schools ahead of the impending September closure. Our team urgently requires trades on-site, as completing our school is paramount. We are unable to progress until the […]

Read More
Scroll Up