News

Milton #11 School Opening: Fast-Track Construction Schedule

Provide a construction schedule for Milton 11 catholic elementary school allowing the opening of September 2027 Yes. Based on the current information available as of August 28, 2026, a September 2027 opening

Milton 11 CES – Foundation Wall Construction Progress Update

We are excited to share that we have successfully completed 100% of the footings, and we’re now preparing to construct our foundation walls. The southern area of the building remains

N E Oakville High School Project: Milestones and Progress

Office I asked Ai to provide a summary and review of our project: Below is the result Yes. I researched the project timeline and can give you a construction-progress timeline beginning

N E Oakville High School – Summer Project Update: Flooring and Exterior Work Insights

As we find ourselves in the midst of a summer lull, there is a sense of complacency that needs shaking off. We are optimistic that our flooring contractor will commence

Milton 11 CES – Construction Update: Footings Completed and Next Steps

Footings are nearing completion, with about 90% of the work done. We’re now poised to kick off the installation of our mechanical and electrical (M&E) underground systems. During my site

N E Oakville High School -Project Progress Update: Contractors Onsite

As we push ahead with our project, I’m pleased to announce that we now have both the flooring contractor and metal siding contractor onsite. While this progress is exciting, the

Milton 11 CES – Current Footing Progress: Key Updates on Construction

Footings are currently in progress and once they are poured, we will reach approximately 75% completion of the footings.. The backfilling of the foundation walls has commenced, enabling the mechanical

Scroll Up