News

Milton 11 CES – construction progress – Oct 13 2026

The masonry contractor is working on the above-ground structures, while the plumbing contractor needs to install underground piping on the west side. To expedite progress, it is crucial to collaborate

N E Oakville High School – construction progress – October 9

The flooring installation in our classrooms has put us behind schedule, as we’re still waiting on the arrival of the installers. Millwork cannot proceed until the finished floor is in

Milton 11 CES – construction progress – Oct 6 2026

The masonry contractor is currently advancing with the construction of walls above ground. However, a significant challenge we face is the delay in receiving steel lintels and metal door frames,

North East Oakville High School – const progress – October 1

As we continue making significant progress on our classroom renovations, I wanted to inform our flooring contractor that all access from the cafeteria to the upper floors will be closed

Scroll Up