St. Kateri Tekakwitha – const progress – June 6 Certified Drone Pilot 2 min 3 years ago 5 Galvanized exterior lintels are required for the 2nd floor east. Load bearing walls have already been built, and once window lintels are in place, we can proceed with the placement of precast for the 3rd floor. Our goal is to have everything […] Share this: Share on Nextdoor (Opens in new window) Nextdoor More Share on Reddit (Opens in new window) Reddit Like this:Like Loading... June 6, 2023
Protected: St. Kateri Tekakwitha – June 1 2023 construction progress Certified Drone Pilot 3 min 3 years ago 3 There is no excerpt because this is a protected post. June 1, 2023
Galvanized exterior lintels are required for the 2nd floor east. Load bearing walls have already been built, and once window lintels are in place, we can proceed with the placement of precast for the 3rd floor. Our goal is to have everything […]