HAPPY Halloween – St. Kateri Tekakwitha

Great news! The installation of the open web steel joist in the west section is 80% complete. This is a major milestone that brings us closer to our project’s completion. In addition, we have the metal deck scheduled to arrive in the […]

Read More
Read More

St. Kateri Tekakwitha – construction progress – Oct 26 2023

Bottom left Sept 26 2023 – Bottom right Oct 26 2023 one month progress Steel – West / Gym 4th floor East- installation exterior lintels Electrical Primary now Pulled Parking Area – Base for lighting are now in place. Ready for asphalt?????

Read More
Read More

St. Kateri Tekakwitha – const progress – Oct 24, 2023

Great news! Tomorrow, the exterior lintels on the 4th floor east are scheduled for installation. This marks a significant milestone in the construction progress, allowing the masonry contractor to proceed with their work. The installation of these lintels will provide structural support […]

Read More

St. Kateri Tekakwitha – Const Progress – Oct 19 2023

The progress of the construction project, particularly concerning steel and exterior galvanized lintels, has become a matter of concern. The General Contractor has confirmed that the Slab on Grade in the Gym, Cafeteria, and Atrium will be poured before the arrival of […]

Read More

St. Kateri Tekakwitha – const progress – Oct 17 2023

Great progress is being made on the construction site! The steel joists have been successfully placed in the gym and are ready for welding and inspection. Once that is completed, the steel deck can be installed. On the second floor West, the […]

Read More