Month: October 2023
St. Kateri Tekakwitha – construction progress – Oct 26 2023
Bottom left Sept 26 2023 – Bottom right Oct 26 2023 one month progress Steel – West / Gym 4th floor East- installation exterior lintels Electrical Primary now Pulled Parking Area – Base for lighting are now in place. Ready for asphalt?????
St. Kateri Tekakwitha – const progress – Oct 24, 2023
Great news! Tomorrow, the exterior lintels on the 4th floor east are scheduled for installation. This marks a significant milestone in the construction progress, allowing the masonry contractor to proceed with their work. The installation of these lintels will provide structural support […]
St. Kateri Tekakwitha – Const Progress – Oct 19 2023
The progress of the construction project, particularly concerning steel and exterior galvanized lintels, has become a matter of concern. The General Contractor has confirmed that the Slab on Grade in the Gym, Cafeteria, and Atrium will be poured before the arrival of […]
St. Kateri Tekakwitha – const progress – Oct 17 2023
Great progress is being made on the construction site! The steel joists have been successfully placed in the gym and are ready for welding and inspection. Once that is completed, the steel deck can be installed. On the second floor West, the […]
Our Bee and Sunflower Farm
I recently had the pleasure of visiting Meijerinks Bee farm, located just on the edge of town. It was an incredible experience that I will cherish for a long time. I would like to express my deepest gratitude to Gary and his […]


Great news! The installation of the open web steel joist in the west section is 80% complete. This is a major milestone that brings us closer to our project’s completion. In addition, we have the metal deck scheduled to arrive in the […]
Share this:
Like this: