St. Nicholas CES – Electrical Duct Bank

0 Comments

As per discussion on site today: It was revealed/ now would be a good time to remove existing elec duct bank and replace with new- prior to precast. I am told Everstrong to remove existing elec duct and CEC build a new elec duct. Please initiate the paperwork allowing this task to be complete ASAP. […]

St. Nicholas CES- construction progress April 18th

0 Comments

Note: Permit Drawings ( Site Service ) are now onsite/ construction trailer! We are pouring slab on grade / classrooms/ Monday! We are pushing 100% SOG prior to May 1st! Waiting for Steel Columns followed by precast!👀👀👀👀👀 Video below shows progress to date! www.larryarbuckle.com 🦅🦅🦅🦅🦅

St. Nicholas CES – April 16, 2019-onstruction progress

0 Comments

Site Services Permit is ready and I will pick up Thurs morning and deliver to site. Weather has not co-operated and we now our pouring slab on grade Monday. The day before our site meeting hmmm! We are still pushing 100 % slab on grade prior to May 1st. M&E contractors are staying ahead of […]

St. Nicholas CES- plumbers worked all week-end

0 Comments

Plumbers worked all week-end allowing slab on grade to be poured this week! Keep masonry contractor going! Everstrong to install expansion joint, poly and re-bar/ for interior walls! 🎯🎯 Work continues! We are pushing slab on grade to be 100% complete prior to May 1st Site Services now on deck Where are we with precast??????? […]