St. Nicholas CES – Electrical Duct Bank
As per discussion on site today: It was revealed/ now would be a good time to remove existing elec duct bank and replace with new- prior to precast. I am
Drone Pilot
As per discussion on site today: It was revealed/ now would be a good time to remove existing elec duct bank and replace with new- prior to precast. I am
Below in blue are the areas we are pouring slab on grade next Thurs – May 2nd Preparing slab on grade for next week 2 guys standing in the back
Note: Permit Drawings ( Site Service ) are now onsite/ construction trailer! We are pouring slab on grade / classrooms/ Monday! We are pushing 100% SOG prior to May 1st!
Continue readingSt. Nicholas CES- construction progress April 18th
Site Services Permit is ready and I will pick up Thurs morning and deliver to site. Weather has not co-operated and we now our pouring slab on grade Monday. The
Continue readingSt. Nicholas CES – April 16, 2019-onstruction progress
Plumbers worked all last week-end pushing slab on grade! http://www.larryarbuckle.com Today’s Flyover
There is no excerpt because this is a protected post.
Plumbers worked all week-end allowing slab on grade to be poured this week! Keep masonry contractor going! Everstrong to install expansion joint, poly and re-bar/ for interior walls! 🎯🎯 Work
Continue readingSt. Nicholas CES- plumbers worked all week-end
There is no excerpt because this is a protected post.
You must be logged in to post a comment.