Nelson High School- May 25/20 construction update
Video below is for Elevator People Same video below but for Construction People
Bishop Reding – May 25/20 update construction
Addition Going Forward Painters are working 2nd floor. Main floor is ready for ceramic tile . Flooring needed classrooms. Followed with Millwork We are ready for whiteboard and tack board
Continue readingBishop Reding – May 25/20 update construction
Thomas Merton May 22/20 renovation update
I believe we have ripped out most equipment and material as we start to rebuild. Duct is being placed in ceilings, Drywall contractor is onboard, and new lighting fixtures are