St. Kateri Tekakwitha construction update – March 28/23
Site Service/ scheduled to start Monday. We are in dire need of steel! M&E contractors are progressing well as undergrounds are being placed @ great speed. Our Masonry contractor is “killing it” but steel is required. Discuss at next site meeting. Above […]
St. Kateri Tekakwitha – construction update- March 23/23
Plenty of people onsite today as we push SOG 1st-2nd week of April. Thought today : we pour the west side first- prior to the arrival of Masonry Contractor. We can discuss at next site meeting. Also we are pushing precast / […]
St. Kateri Tekakwitha CHS – March 14/23 construction update
Plumbing / underground is progressing well / working on the north west hallway. Scaffold and planks have arrived re- masonry. Here we go! Masonry contractor building north-east corridor. Plumbers working north – west corridor – exiting the building. Masonry contractor unloading scaffold […]


1 min- 0 0
-
193
-
3 years ago
- 1
- 3
Construction progress is proceeding extremely well as it’s great to see everyone planning and working together. EVENTS: 1 – our first lift of precast /east/ scheduled first week of May. 2 – all steel and masonry to be complete /east/ prior to […]
Share this:
Like this:
-
- | Leave a Comment on St. Kateri Tekakwitha- construction progress- March 31/23
Tagged construction, construction Management, DJI Spark, General Contractor, Hangar