Childcare – We have elected to backfill Foundation Walls knowing we have frost. Once building footprint is levelled allows masonry contractor to erect walls. We have decided to pour SOG at a later date. Cafeteria- I am told steel erectors /Mirage/ arrive tomorrow.👍Cafeteria- column /base/ has now been Poured. We are good to go.Addition- locker bases are being poured.Masonry contractor has staff onsite rubbing walls and cleaning door frames. I am told painters will be onsite tomorrow painting door frames and walls.