Bishop Reding – May 25/20 update construction

Blog Summary: (AI Summaries by Summarizes)
  • The post discusses the importance of executive summaries for busy individuals.
  • It emphasizes the need for concise and clear communication in executive summaries.
  • Executive summaries should provide a brief overview of the main points and key findings.

Addition

Main Floor- framing of T-bar ceilings near completion
Classrooms- lighting fixtures now in place.
Ceramic tile now onsite- corridors.
Railings in place- stairwell
Millwork- metal cabinets onsite.

Going Forward

Painters are working 2nd floor. Main floor is ready for ceramic tile . Flooring needed classrooms. Followed with Millwork

We are ready for whiteboard and tack board – classrooms / Now!

Installation of lockers 1st week of July

Hanging classroom doors Aug 1st.

Cafeteria

Looking out at New Entrance.
New Kitchen
New Cafeteria

Childcare

Exterior walls have now been erected.
All walls scheduled for completion middle of next week . Ready for steel is next.
Note: steel columns must be in place allowing masonry walls to be complete.

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll Up

Discover more from L A Drone

Subscribe now to keep reading and get access to the full archive.

Continue reading