N E Oakville H S -Progress Update: Lakeside Project Completion Timeline

Blog Summary: (AI Summaries by Summarizes)

We are Ready for Lakeside – ensure all exterior is free from material , equipment and garbage.

Floor tile installers in the hallway are near completion on the 3rd floor. They are scheduled to begin work on the 2nd floor hallways by midweek. We are now waiting for the flooring contractor in the classrooms to mobilize as soon as possible. We await Lakeside to complete their contract on the exterior, and once that is complete, it will allow our landscape contractor to continue. Next in line is our millworker, followed by the lockers. We need everyone on board as we approach the finish line.