N E Oakville High School – Project Update: Ceiling Installations and Upcoming Tasks
Project Update
The installation of the T-Bar ceilings in classrooms and hallways is currently underway and on schedule. We are now shifting our focus to the installation of light fixtures, flooring, millwork, and chalk and tack boards.
Action Items for Aerloc
- Please prioritize the completion of all glass installations and the exterior windows. Your timely work is crucial as any delay is impacting the progress of other trades.
Upcoming Schedule
- Parking concrete curbs are set to commence this Friday.
Conclusion
With the finishing trades now on board, we must all collaborate to ensure that they can perform their work efficiently. We are officially in the finish mode, and it’s essential that we all make a concerted effort to allow progress in this phase.