N E Oakville High School – School Construction Progress: Key Updates and Upcoming Tasks

Asphalt Next Week

Main Mechanical Room

Project Update: School Construction Progress

Current Status

  • Metal Decking: The metal deck on the north side /roof/ of the school has been successfully placed.
  • Welding: Ongoing welding of open web steel joists on the south side is progressing well, with metal deck installation expected during the week of December 8th.

Upcoming Tasks

  • Parapet Walls & Curbs: Once the parapet walls are constructed and all curbs are in place, our roofing company, GRRC, will mobilize to ensure we become watertight as soon as possible.
  • Window Installation: Windows are scheduled to arrive before Christmas, with installation set to begin immediately thereafter.
  • Painting: If the aforementioned tasks are completed on schedule, our painters will begin work during the first two weeks of the new year.

Asphalt and Parking Area

  • Asphalt Installation: The asphalt for the parking area is scheduled to commence next week.

Conclusion

Progress is being made steadily, and the project is coming together. Stay tuned for more updates!

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll Up

Discover more from L A Drone

Subscribe now to keep reading and get access to the full archive.

Continue reading