The weather looks promising as we move forward with the final touches on the exterior, focusing on asphalt, sidewalks, curbs, landscaping, and the installation of parking lighting fixtures. The pace of work outside is set to intensify, and with this momentum, we aim for a successful opening on January 1st.
Internally, we also need to quicken our efforts, starting with heating the building. I want to highlight that we will be flushing the boiler system next week, which should result in a comfortable heat throughout the facility. The next two months are pivotal, and it’s essential to have our team on site to ensure everything progresses smoothly.
Additionally, AERLOC, we urgently require windows, as relying on plywood for covering windows and doors is not a viable solution. It’s crucial to prioritize safety and efficiency in the coming weeks. Therefore, if anyone has a medical condition, it is advisable to stay home during this critical period to avoid any complications. Our collective commitment during this time will be pivotal to our successful completion and opening. Let’s keep our focus sharp and ensure we meet our objectives.