St. Kateri Tekakwitha CHS – construction progress – Oct 10/23

Blog Summary: (AI Summaries by Summarizes)
  • The masonry contractor is currently working on the 4th floor east, but there is a delay in the arrival of the steel lintels.
  • A contingency plan has been made to build concrete bond beams instead of using steel if the lintels do not arrive in time.
  • The general contractor is preparing to receive the topping on the 2nd floor west, with the first pouring of concrete scheduled for Friday.