St. Nicholas – 20 days remaining

Blog Summary: (AI Summaries by Summarizes)
  • The post discusses the importance of executive summaries for busy individuals.
  • It emphasizes the need for concise and clear communication in executive summaries.
  • Executive summaries should provide a brief overview of the main points and key findings.
Fence needed – kindergarten play area
Backfill behind curb needed. We have plenty of topsoil onsite / to complete this task. Area behind curbs -cut to sub grade.
Aerloc needed to install glass fire separation stage [as per above] also all exterior doors and windows.
Flooring- ceramic tile and sheet goods are of concern. Hopefully Zetmaster Flooring can provide more manpower as Max [ on his own] will not be able to complete in 20 days. As per above picture ceramic tile / washroom walls / need to be installed / ASAP/ allowing installation plumbing fixtures / sinks
As scheduled. All above ceiling work needs to be complete prior to Dec 2. All ceiling tile -scheduled to be placed after the 2nd.

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll Up

Discover more from L A Drone

Subscribe now to keep reading and get access to the full archive.

Continue reading