St. Nicholas CES- standing room only

Site is very busy today as precast continues being placed! If you stand still on this job you will receive “windburn”

Site Service contractor has dropped off piping and scheduled installation this week!

Masonry contractor now on 2nd floor! Open Web Steel Joist to arrive -end of this month- Roof start mid July. Mechanical equipment arrive the week of June 17th. Housekeeping pads to be in place.

Paving contractor to follow site service contractor with stone- prevent mud!

On Deck- windows