2nd floor is near completion. As a footnote: once we are successful with fire verification allows school board to load their furniture / 2nd floor only. Starting Dec 16.
Admin office near completion with T-bar ceiling. Millwork to be installed Monday.
Waiting for toilet partitions.
Front lobby has now been taped and sanded. Painting starts Monday followed with ceramic tile.
Flooring contractor near completion / classrooms 2nd floor. George /Zetmaster/ said he is bringing in an extra crew Tuesday. General Contractor to ensure all classrooms are emptied and swept. George said he plans to be complete /all classrooms/ prior to Dec 20👍👍
Ceramic tile/ washroom walls/ near completion
HM screens being installed separating front lobby from library.
Parking / asphalt / near completion. We only need one good day next to complete this task.
NOTE: The only wild card is Aerloc. They are scheduled next Tuesday re- installation of exterior doors & windows, interior glass And fire separation / stage. Without this we are “done like dinner” stay tuned for a dramatic ending.

Author

larryarbuckle@gmail.com
Fly high and stay dry.headset

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Scroll Up

Discover more from L A Drone

Subscribe now to keep reading and get access to the full archive.

Continue reading