Construction Update: Progress on Painting and Roofing – North East Oakville High School – May 28 2026
- The gym is being painted before it becomes a storage area, emphasizing the importance of timely completion.
Below : good time to paint the Gym before it becomes a storage area!!
The pace has picked up as more trades are now onsite. Painters are currently painting the featured colour walls, and the framing for the T-bar ceiling has begun. It is crucial that all work above the T-bar ceiling is expedited. The roofers are nearing completion and are preparing to demobilize. Aerloc, we need you to finish all window installations to ensure we achieve 100 percent watertight conditions. The weather is cooperating, allowing all exterior work to proceed as planned. It’s exciting to see everything starting to come together.