Oakville North High School – const progress – Nov 26 2026

Blog Summary: (AI Summaries by Summarizes)

Exterior construction is progressing well. Sod is being placed on the practice field, while the concrete curbs are nearing completion. Sidewalk installation will follow.

With the weather forecast calling for above-average temperatures in the coming weeks, attention is turning to the possibility of placing the base asphalt and completing the top coat, including line painting. This work could help bring Lakeside’s contract closer to completion. Before that can proceed, all materials and equipment will need to be removed from Lakeside’s current working area.

Inside the facility, we have supplied temporary propane heat while we await the start-up of the permanent boilers, which is currently estimated to be two to three weeks away. Once the boilers are operational, the propane heaters will no longer be required.

Flooring installation has now begun on the main floor, marking another important milestone in the project. In addition, our lockers are scheduled to arrive onsite next week. Their installation will further advance the interior build-out and help bring the facility closer to readiness.

Although there is still work to be completed both inside and outside, the progress is becoming increasingly visible. The practice field is taking shape, exterior concrete work is nearing completion, and major interior installations are underway. With each phase moving forward, we can now see light at the end of the tunnel.

Below – flooring in admin office scheduled for next week