St. Kateri Tekakwitha – construction progress Sept 5/23

Blog Summary: (AI Summaries by Summarizes)
  • The Masonry Contractor is scheduled to complete the 3rd floor on the east end of the building by the end of this week.
  • Topping and precast installation are the next steps in the construction process.
  • The masonry team will shift their attention to erecting walls on the west side of the building next week.
Above left picture AUG 31 – Right pic SEPT 5/23