St. Nicholas CES- 63 days remaining

Arrowhead Paving is now on our critical path. 🎯🎯
Aerloc is onsite installing glass👍
The building needs a major clean up.
Brick veneer starting in the front.
Roof is only 45% complete. This has been a long process.
Arrowhead Paving starts next week.