Month: September 2018
St. Mark CES- construction update
Stage: Sprinkler contractor has now placed their pipe! We await the return of our drywall contractor (Cannan) installing grid. Once installed allows the placement of lights, sprinkler heads and diffusers! Precast arrives Monday! I am told hollow metal frames (doors) arrive tomorrow! […]
St. Mark CES- precast arrives Oct 1st
This project will be firing back up Oct 1st as we are scheduled for precast! Once placed, sprinkler and plumbing pipe can be hung as well as electrical conduit! As discussed, we are pushing for a Jan 1st 2019 completion! Ensure all […]
Bishop Reding Catholic High School
Work starts this fall – stay tuned
St. Mark CES- awaiting precast
Pre- cast has been delayed (2nd floor) until the first week of October! That being said: going forward please ensure all material is onsite starting with: -All remaining hollow metal frames (doors) are onsite ( TRP) – all Lintels (galvanized) and plates […]
St. Mark CES- awaiting precast
We have scheduled Oct 5th as are precast drop. The school has scheduled a P.A. Day resulting in teachers and students not being onsite. TRP and PSI please connect Also note: once precast is placed / load bearing masonry walls to be […]
St. Mark CES- construction progress
We are pushing to complete addition prior to Christmas. Gymnasium- starting to install metal duct. Lights and fans to follow. We are scheduled for completion / 2-3 weeks. Construction progress – south- west corner Construction progress north-east corner Construction progress north-west corner […]


North West corner South west corner South east corner North east corner Aerial 1 Aerial 2 Aerial 3 “Lead, Follow Or Get Out Of Way”