Month: October 2019
St. Nicholas- Oct 29/19 flyover
Roofing is ongoing. Concrete curbs being poured /parking area. Let’s start thinking roughing in electrical for overhead parking area- lighting. 46 days remaining.
St. Nicholas- pic of day
T- bar grid is going up! http://www.larryarbuckle.com π¦ π¦ π¦ π¦ π¦
St. Nicholas – 46 days remaining
We are βrock-n- rollβ on the exterior. Arrowhead is onsite setting string for concrete curb. All curbs to be poured tomorrow.πππππ
You must be logged in to post a comment.