Auto-body classroom- contractor is onsite installing equipment.

Health Rm- demolition continues as contractor removes a masonry wall.

Tech rms.- building of masonry walls continues.

Washroom ready for completion.

Many openings in need of door frames, doors, hardware, floor repair and painting.


Manhole is now in place. Waiting on Masonry Contractor / building shaft re- elevator.

Admin Office- framing has started.