“Is there a doctor in the house” blood pressure is running high!
Very busy today as we have plenty of activity, Below, our plumbers are placing underground pipe. We are scheduled to pour our SOG this Friday. Stay tuned as we rebuild!
Floor for food nutrition room also to be poured Friday!
We need door jambs installed ASAP
Floor re- exit to be also poured on Friday
The Canann boys (drywall) are here and starting ceilings in our change rooms👍
We are starting T-bar ceilings in the computer room
RRG working – natural play area!
RRG to remove their piles of dirt and debris by Friday!
Roof Top Units are being placed- we need steel to be complete yesterday. Victor is doing a great job as when steel is complete allows us to rebuild. Charge!
Portables are scheduled to be relocated this week. We are starting our new parking area next week👍
We have only 36 days remaining👀👀👀👀