N E Oakville HS – Rooftop Units Installed: Construction Project Update

The construction project has reached significant milestones, as all rooftop units are now installed, achieving a 100% watertight status. The gym floor is equipped with acoustic flooring, anticipating the upcoming topping pour. This week marks the commencement of the flooring contractor’s work, […]

Read More

Milton 11 CES – Construction Progress Update: Foundation Footings Begin

Our friends at D’Orazio are making great strides in the northwest corner, enabling us to advance our footing work. This week, we are commencing the footings on the front half of the building. Soon, we will begin backfilling our foundation walls, which […]

Read More